Project Information
Final Contract: $1,690,270.00
Client: City of Fort Lauderdale
View Scope Details
Scope Of Work
The work includes demolition of existing restroom building, sidewalks, curbing, existing aerial utilities. Also included the undergrounding of FPL/Comcast services new and exist., site lighting, utilities water, sewer and fire systems, ADA walks, resurface parking, new ADA parking layout, ADA restroom/Fish cleaning station bldg., picnic area, landscaping and irrigation.
As part of the work performed on the water was the reinforcing of existing sea wall and new seawall cap, complete new dock systems to include pilings, floating docks, and marina stations with water, sewer systems, electrical and fire service to service boats.